Utilisation answers two questions. Of every hour you paid for, how much was real work on a job? Of every working day a machine was on the fleet, how many did it spend on a job? It has two tabs, People and Machines, and one Period for both.
Who can use it — Anyone with "view budget tracking" permission. Recovery and rate-book figures also need "view margin". A person's cost per hour needs "view pay level rates". Machine money needs asset cost access. See Roles & Permissions.
Where to find it — Costs & Budget → Utilisation in the sidebar.
Before you start — the figures come from days posted to the Budget Ledger. A day appears once it is posted. The line under the filters says how complete the figures are; View issues lists each gap and where it is fixed.
The period
Period sets the window for both tabs: the last 12 months, this or last financial year, or your own dates. Click a month in a chart to see that month. Figures stop at today, and machine days stop at the last day plant was posted.
People
The first screen
- Data incomplete (or No gaps found) names what the figures rest on: part of the period posted, breaks estimated, hours with no cost, hours with no rate-book rate.
- Paid hours, Effort hours, Effort % and Cost per effort hour. Each is marked Recorded, Estimated or Incomplete, and each opens its breakdown.
- Under each figure, how it moved on the period just before — for a whole month, on the month before. It shows only when that earlier period was posted from its start.
- Utilisation in one line: the share of paid hours earned, unknown and not earned. It leads to Recovery.
- Needs a look lists exceptions, one row per kind, most hours first. Show each one opens the names.
Where the paid hours went
Paid hours are walked down to effort hours: leave, public holidays, paid travel, rain, stand-down, yard time, paid breaks, paid prestart and recorded delays come off. Change chooses which of these count as not effort. A step with no hours is named in one line under the walk rather than shown as a row.
By role and by person
Each person counts under the role they worked most hours as. People who only took leave in the period are grouped as Leave only. Click a column to sort. Click a role to narrow the page to it. Click a person for their own panel: their walk, what is missing for them, their months and the timesheet entries behind the figures.
Recovery
What the hours earned against what the rate book charges for them. Day-works hours earn the labour hours on the job's dockets. Contract hours earn what the work was worth. Open a job for its working. Work with no earned value recorded, or with no rate-book rate, counts as unknown, never as zero.
Invoiced appears once a sales invoice is matched to a job in the period.
Day works logged as contract
Sometimes a day's dockets cover more hours than were logged as day works: the work was done and docketed, but typed as contract on a timesheet. View issues → Review the entries lists those entries. With "manage day works dockets" permission you can tick the ones the docket covers and Mark as day works. Nobody's pay changes and no posted cost moves; the hours count as day works on the timesheet and in Day Works coverage.
Planning
Planning turns the period's figures into a scenario: a dry year, a typical full-time year, and what each role must charge at your target margin. A role under its target links to the Rate Book. Back to actuals leaves the scenario.
Machines
The first screen
- The status line says the span the days cover, how many machines have a fleet cost, and on how many job days running hours are recorded.
- Available days, Days on a job, On a job % and Running hours.
- Needs a look: machines never on a job, machines on a job with no hours recorded, machines that left the fleet with no date, and classes with no day rate. Each leads to its list or its fix.
Where the machine-days went
Available days are the working days each machine was on the fleet. Grounded days, days in the yard and days with no job recorded come off, leaving days on a job. A day on a job is a day charged to one at its internal day rate.
Running hours and meters
Running hours come from operators' approved timesheets, and only those are used for costing. Where a machine has two or more meter readings in the period, the page also shows Meters: its last reading less its first. A reading that falls well below the one before, or is further on than the meter could have run, is left out and listed under View issues so it can be corrected.
By class and by machine
Click a column to sort. Open a class for its days and what they rest on. While the list is least used first, machines never on a job sit in their own group.
Click a machine for its panel: its days, the jobs it was on, the runs of days nobody said where it was (each opens that week in the Allocation Manager), its running and meter hours, and what is missing for it.
Yard plant
A forklift or a yard trailer is not expected on jobs. In Asset configuration, open its class and turn on Yard plant — not expected on jobs. Its machines are then left out of the percentages and counted on their own line under View issues.
Cost and recovery
Fleet cost against what was charged to jobs. With a fleet cost on fewer than half the machines, no figure is shown: add fleet costs in Asset Costs first.
Planning
Planning holds your Target days on a job and Target margin, and what each class must be charged: break-even days and the day rate needed.
Passing it on
Download the summary, beside the Period control, gives the tab on screen as a PDF: its figures, where the hours or days went, the breakdown by role or class, what needs a look and what the figures rest on. It carries the period and filters in force, and shows no money to someone the screen would not. It is an internal summary, not a client document.
Good to know
- An unknown is never shown as zero. "Not recorded" means the record is missing, not that nothing happened.
- Earned value belongs to a whole job, so Recovery steps aside when you narrow People to a role or a person.
- Hired-in plant is not counted as fleet. It is listed against your own idle machines of the same class.